Category 5 Handbook
You are visitor
number
.
Related Links

In early March, 1996, inspired by California's well-organized
NetDay,
the idea of a Mary Blair NetDay was hatched. Originally, we
planned to wire five classrooms with two Category 5 lines each, plus
the Media Center with two lines.
With generous support from the PTO, the Student Council, and the Principal,
we eventually received enough funding to cable every one of the 23
(twenty-three) full-sized classrooms, except Art and Music. Each
classroom was to receive two Category 5 lines and the Media Center
was to receive four Category 5 lines.
[Click
here
to view the floor plan of Mary Blair Elementary School.]
On Saturday, March 30, 1996, about a dozen volunteers worked at the
school for three to six hours each. We pulled our first nine cables.
Work continued throughout April, with a small group of volunteers
working after school or nights once or twice a week plus Saturday,
and with one or two volunteers working many additional afternoons,
nights, and Sundays.
On Sunday, April 28, 1996, the volunteers completed termination of
the patch panel and the last of the 50 (fifty) Category 5 cables.
At 3:30 PM on Wednesday, May 1, two professional cablers from Collins
Control in Fort Collins brought their best test-equipment to test and
certify our installation. By 5:15 PM, our new infrastructure was certified
as 100% Category 5 compliant!
[Click
here
to view the floor plan with Category 5 information.]
Since the lead volunteer will not always be available at Mary Blair,
the purpose of this handbook is to document the installation guidelines
that allowed us to achieve 100% Category 5 compliance.
Obviously, this handbook should be consulted whenever any Category 5
cabling modification is planned or performed.
Less obviously, this handbook should also be consulted whenever any
lighting or AC wiring changes are planned or performed.
INDUSTRY STANDARDS
All cables were UL-listed type CMP or MPP (plenum-rated communications cable).
All cables were UTP (unshielded twisted pair), 4 pair, 24 AWG, EIA/TIA 568,
verified Category 5.
All terminations at the jacks and at the patch panel were T568B.
(AKA AT&T 258A). The jacks and the patch panel were rated as Category 5.
All terminations at the jacks and at the patch panel used 110-style
punch-downs.
In most classrooms, the existing IBM Baseband LAN jacks were replaced.
The replacement jacks were 6-conductor USOC with 110-style punch-downs.
No other modifications of any kind were made to the existing IBM Baseband
LAN.
In one or two cases, a modem or voice jack was replaced. The replacement
jacks were USOC jacks with 110-style punch-downs.
MBE STANDARDS
Cable designations:
Each cable was uniquely identified and labeled on both ends as it was
pulled. Typical designations for the two cables to a classroom were
201/A and 201/B. These labels were removed from the cables as they
were punched down on the patch panel. But the labels were generally
left on the cables inside the box in the classrooms.
Jack color codes:
The first cable to a classroom (cable A) is always connected to a blue jack.
The second cable (cable B) is always connected to a red jack.
The third cable (Cable C) is connected to a purple jack. (Only the media
center has more than two cables at this time.)
The fourth cable (Cable D) is connected to a yellow jack.
Blue, red, purple, and yellow jacks are always rated as Category 5.
The rewired IBM Baseband LAN jacks are white.
The rewired voice-grade (voice, modem, or AT&T Spirit) jacks are ivory.
Patch-panel color codes and positions:
The patch panel is marked with a room number. The color of the markings
or the color of the background corresponds to the color of the jack in
the classroom.
Patch panel ports for a given room are always adjacent to each other.
The ports are always in order from left to right (blue, red, purple,
yellow).
Note: This standard ordering is important for those who are colorblind.
Coverplate and jack positions:
Coverplates were always 4- or 6-position ivory.
Unused positions were always filled with ivory blanks.
The Blue jack, if present, is always in the upper left position.
The Red jack, if present, is always in the upper right position.
The White jack, if present, is always in the lower right position.
The Ivory jack, if present, is always in the lower left position.
In several cases, an existing box was mounted horizontally. In this
case, the above position scheme was used when installing the jacks in
the cover plate. Then the cover plate was rotated 90 degrees and
installed over the box.
Note: This standard positioning is important for those who are colorblind.
Parts list:
The patch panels and all jacks and coverplates are manufactured by
Leviton Telcom. Leviton part numbers are listed here for reference:
- 41080-4IP 4-port wallplate, ivory
- 41080-6IP 6-port wallplate, ivory
- 41084-BIB Blank inserts, ivory
- 41108-RL5 Category 5 jack, blue
- 41108-RR5 Category 5 jack, red
- 41108-RP5 Category 5 jack, purple
- 41108-RY5 Category 5 jack, yellow
- 41106-RI6 USOC jack, 6P6C, ivory
- 41106-RW6 USOC jack, 6P6C, white
- 41777-IBB Surface Mount Box - 1.45" deep, ivory
- 49484-B24 24-port Category 5 patch panel, 568B, 110, black.
CATEGORY 5 CABLE LENGTH GUIDELINES
EIA/TIA 568 specifies a maximum length of 100 meters (approximately 328
feet) from the hub to the computer. 90 meters (approximately 300 feet)
is allowed from the patch panel to the jack in the classroom. 6 meters
(approximately 20 feet) is allowed from the hub to the patch panel.
3 meters (approximately 10 feet) is allowed from the jack to the computer.
In an office environment, the 90/6/3 allocation is reasonable. In a
30' x 30' classroom, a 3 meter cable is often unreasonable.
An alternative is to tally the distance of each of the three components
of the cabling system. The patch cable connected to the hub and the
patch cable connected to the computer must be measured at 120% of their
actual length. [Patch cables are more flexible than building wiring,
but have poorer electrical characteristics.]
The longest cable run in MBE is currently about 255 feet. In practice,
a 30 foot patch cable in the classroom should not strain the
Category 5 distance limitations.
CATEGORY 5 CABLE ROUTING GUIDELINES
- Unlike ordinary telephone cable, Category 5 specifications do not
permit a splice in the cable. If a cable is damaged, a completely new
cable must be installed.
- Do not allow the sheath of Category 5 cable to be damaged. In
particular, avoid pulling cable across rough surfaces such as
concrete or sharp edges of angle-iron.
- The minimum bend radius of Category 5 cable is variously
recommended at 2 to 4 inches. (Remember a circular loop would
have a diameter twice the radius!) Observe the 4-inch minimum
bend radius at all times except at the two points of termination.
If possible, observe the 2-inch minimum bend radius at the jack
and at the patch panel.
- Never allow a cable to be kinked while handling it. If a kink
begins to form while pulling cables,
STOP!
- When pulling cable up into the ceiling or around a corner, it is
usually necessary to have a human "feed" the cable to prevent the
minimum bend radius from being exceeded.
- Never route Category 5 cable within 18 inches of a flourescent
light fixture.
- Never route Category 5 cable within a few feet of large motors
or power transformers.
- When running Category 5 cable parallel to line voltage, always
keep a separation of 5 inches or more, even if the line voltage is
enclosed in conduit.
- When running Category 5 cable across line voltage, try to keep
a separation of 5 inches or more. An occasional separation of
slightly less than 5 inches is acceptable. In particular, avoid
laying Category 5 cable directly across conduit containing line voltage.
- Make liberal use of "beam clamps" and "bridle rings" to route
the cable where
you
want it to go, not where the cable would tend to go on
its own.
- Category 5 cable should be essentially circular. When using
cable ties on Category 5 cable, do not tighten the cable tie to
the point that the cable deforms. As a general rule, the entire
bundle of Category 5 cable that is tied should be able to slide
freely back and forth inside the cable tie.
- Modern building codes preclude Category 5 cables from being
tied to electrical conduit, water or steam pipes, air-ducts,
drop-ceiling wires, etc. In general cables should be supported by
structural components of the building such as steel beams. Tying
to steel supports such as All-Thread, which are themselves attached
to structural steel or concrete is also acceptable. Use two cable
ties where necessary. (One cable tie firmly gripping the steel and
a second cable tie. The second cable tie loosely holding the Category
5 cables.)
- Modern electrical and fire and safety codes require only UL-listed
communications cable be used. Although we found some existing non-plenum
rated cable in the west wing, we believe the entire south and west wings
of Mary Blair Elementary require plenum-rated cable. (UL Type CMP or MPP
are acceptable.)
- Where a bundle of cables must pass through a wall, including a
firewall, install a chase: Use EMT or rigid metal conduit;
install a set-screw connector on each end of the conduit; and install
a nylon bushing on each end of the conduit. The sharp edge of a
concrete-block wall or the sharp edge of an unbushed conduit can
easily damage the Category 5 cables.
- Modern fire and safety codes require careful attention when a
firewall is breached. We believe that nearly all of the previously
installed communications cables (IBM Baseband LAN, telephone, cable TV,
closed-circuit TV, fire-alarm, intercom, etc) pass through firewalls
in a manner that does not comply with current codes.
- In all cases where new communications cable passes through a firewall,
install a chase as described above, fill the chase not more than 40% full
of cables, and install an airtight
plug of Fire Stop caulk inside the conduit to fill the space not occupied
by cables. Install an airtight bead or plug of Fire Stop caulk outside
the conduit to fill the space between the conduit
and the hole bored through the firewall. In the case of a 2-hour firewall,
a minimum depth of 1 inch of Fire Stop caulk is required on each side of
the firewall. In the case of a 1-hour firewall, a minimum depth of 1/2
inch of Fire Stop caulk is required on each side of the firewall.
- The National Electrical Code as well as the UL listing for Fire Stop
caulk, specify that the chases cannot be filled over 40% full, by area.
The volunteers installed 1.25" EMT, whose cross-sectional area is 1.50
sq in. [See 1993 NEC, Chapter 9.] Category 5 cable is approximately
0.2 inches in diameter, but varies slightly with manufacturer.
Eighteen or fewer cables of 0.206 inch diameter may pass through
a section of 1.25" EMT. Twenty or fewer cables of 0.195 inch diameter
may pass through a section of 1.25" EMT.
- Please do not put anything through the chases installed for Category 5
cabling except additional Category 5 cables!
CATEGORY 5 JACK TERMINATION GUIDELINES
- Cable "A" is connected to the blue Category 5 jack.
- Cable "B" is connected to the red Category 5 jack.
- The sheath should be stripped back no more than 1/8" from the back
of the jack.
- Leviton Category 5 jacks are marked with 568A and 568B color codes.
Since we are using the 568B standard, follow the color code marked "B"
on the jacks.
- Each pair should be untwisted as little as possible, and may not
be untwisted more than 1/2" from the point of termination.
- Route the wires down the center of the channel in the jack. Each
of the two wires of a pair should be as nearly the same length as possible.
- Do not damage wire or insulation while punching down other pairs.
Suggest punching down the pair at the rear of the jack first, then
the pair closer to the front, then the two pairs at the front, in
either order.
- Avoid having the pairs cross each other more than necessary.
Suggest rotating cable (or jack) before beginning punch-down
to minimize pair crossings.
- Double-check that all 8 wires are fully punched down, trimmed,
and colors are correct!
- Install strain reliefs.
- When installing cover plate, maintain the largest possible bend-radius.
USOC JACK TERMINATION GUIDELINES
- Remove cable from existing jack.
- Leviton USOC jacks are marked with color codes.
Simply match color code on IBM Baseband LAN cable to color code on jack.
- Route the wires down the center of the channel in the jack.
- Do not damage wire or insulation while punching down other pairs.
Suggest punching down the pair at the rear of the jack first, then
the pair closer to the front.
- Double-check that all 4 wires are fully punched down, trimmed,
and colors are correct!
- Install strain reliefs.
CATEGORY 5 PATCH PANEL TERMINATION GUIDELINES
- Plan the layout of the patch panel before you begin.
- "Comb" the cables as they drop from the ceiling. Suggest bundling
groups of six cables corresponding to groups of six ports on the patch
panel.
- Leave a reasonable "service loop" on each cable, in case it needs
to be reterminated.
- Begin terminating with the topmost patch panel.
- For each patch panel, begin terminating at the side the cables are
fed from. In our case, we unhinge the patch panels and terminate
from left to right on the back of the patch panel, which is from
high port number to low port number.
- Cut each cable to length, such that each cable connected to a single
patch panel will follow the same service loop. Besides looking neat,
the patch panel can be shifted up or down as necessary if new equipment
is added at a future date.
- As a cable is terminated, lay it on top of the previously terminated
cables on the back of the patch panel.
- The 110D connectors on the rear of the patch panel are color coded.
Within each pair, Tip is to the left and Ring is to the right.
Tip is the predominantly white wire.
- Each pair should extend to the right, and then gracefully curve up
or down towards its termination. Avoid ultra-sharp bends and U-turns
in the pairs.
- Each of the two wires of a pair should be as nearly
the same length as possible.
- The sheath should be stripped back no more than necessary.
Suggest stripping the sheath even with where the first pair will be
punched down.
- Each pair should be untwisted as little as possible, and may not
be untwisted more than 1/2" from the point of termination.
- Do not damage wire or insulation while punching down other pairs.
Suggest punching down the pairs from left to right.
- Avoid having the pairs cross each other more than necessary.
Suggest rotating cable before punching down each pair
to minimize pair crossings.
- Double-check that all 8 wires are fully punched down, trimmed,
and colors are correct!
HOW IMPORTANT ARE THE GUIDELINES?
The experts told us that a single major transgression of these
guidelines can cause a cable to fail to perform in a Category 5
environment.
A cable might pass, even with a few minor transgressions of these
guidelines.
Our policy was to follow the guidelines, except in those few
instances where it was extremely difficult to follow them. There
are several instances, especially where only one or two cables
are involved, where the cable routing guidelines were followed
less rigorously.
FUTURE PLANS
Rooms 206 and 208 can be divided into two half-size classrooms or
combined to make one full-size classroom. These two rooms are now
combined to make one full-size classroom. Room 206 was cabled.
Room 208 remains to be cabled.
The volunteers kept some cable on reserve in case of trouble with
the testing. After the network was tested, but before the Fire Stop
was installed, cables were run to room 207. Room 207 remains to be
terminated and tested.
Room 210 is behind its own 1-hour firewall. This room remains to
be cabled.
The multipurpose section of the building is behind its own 2-hour
firewall. This includes the Music and Art rooms, which remain to
be cabled.
The media center needs more ports. It may make sense to install a
small hub in lieu of running a number of additional cables.
The only areas cabled were classrooms and the Media Center. Other
areas may need to be cabled, but were not considered high priority.
COMPARISON WITH DISTRICT PLANS
General plans for the cabling infrastructure (as well as many other
technological topics) are specified in the Thompson School District's
"Strategic Plan for Technology -- A Work in Progress".
More details regarding the cabling infrastructure of the schools are
contained in the above report's Appendix B "Cyberlink Final Report --
March 1995".
We believe the category 5 cabling the volunteers installed is in
perfect harmony with the goals of the Strategic Plan.
We also believe that aside from having a portion of the work done
sooner at a fraction of the cost, the category 5 cabling
is in close harmony with Appendix B and with Appendix H, the Tactical
Implementation Analysis.
The District recognizes that the IBM Baseband LAN is hopelessly
obsolete. For Mary Blair Elementary, the strategic plan recommends
installation of two Category 5 cables plus one telephone cable into
each classroom.
The strategic plan also recommends installation of Category 5 cables
in virtually every area of the building, including the custodial
office, the kitchen, and the boiler room.
Mary Blair Elementary is listed in Appendix B as being a "Phase 3"
school. If ample funding had been available, MBE would have been
cabled by June 1998. However, at the time of MBE's NetDay, funding
was not available, and the cabling was already a year behind
Appendix B's schedule.
The Board of Education is now (circa July 1996) considering a bond
issue that would raise money for this and other purposes.
The total cost of cabling MBE is shown in the plan at $51K. Of this,
approximately $33.5K is for cabling the 28 classrooms, and the balance
is for cabling the Media Center and other areas of the building.
Of the $33.5K designated for cabling the 28 classrooms, $18.6K is for
two Category 5 cables per classroom, and $14.9K is for a telephone
line to each classroom.
At the time the Cyberlink report was prepared, there was a critical
shortage of plenum-rated cable. Therefore, the Cyberlink estimates
were for installing non-plenum cable in conduit. Since this
shortage has abated, the volunteers chose to install plenum-rated
cable without conduit.
The Cyberlink estimates did not include hubs.
Comparison of Costs at Other School Districts
As a point of reference, the
California NetDay '96
experts estimated
the cost to wire a classroom with two Category 5 ports to be $2,800
per classroom, going through the traditional engineering, bid, and
contract process.
The
North Carolina NetDay '96
experts estimate their equivalent cost
to be
$2,250 per classroom.
The Category 5 portion of the MBE portion of the Thompson R2-J Plan
works out to about $660 per classroom ($18.6K divided by 28 classrooms).
The MBE volunteers spent less than $125 per classroom, of which the
majority of the funds came from the PTO and Student Council.
Telephone Lines to Each Classroom
Telephone lines were not treated as a high priority by the volunteers.
Despite this, the volunteers did bring limited telephone service from
the telephone room to the Category 5 patch panel. If a class needs
telephone service for a particular lesson (for example for a
distance-learning application or a modem connection), telephone
service can be brought to that classroom via the patch panel for
the duration of the lesson.
The Plan specifies that existing wiring should be reused wherever
possible. Long term, the lead volunteer questions whether new telephone
cables to each classroom are required.
Every classroom has an IBM Baseband LAN connection, which will be
phased out eventually. Therefore, every classroom is already wired
with two pairs of better-than-telephone grade cable.
Each classroom's Baseband cable connects to one of four IBM Baseband Hubs
at one of three locations throughout the school. Each Baseband Hub can
serve up to ten classrooms.
Why not run a 25-pair telephone cable (or five to ten 4-pair Category 3
cables) from the telephone room to the current location of each Baseband
Hub. When the old baseband LAN is phased out, splice the old classroom
baseband cables onto the new telephone cables.
Even if it is decided to run a separate telephone (or Category 3)
cable from the telephone room to each individual classroom, the
materials costs should be significantly less than the costs involved
for the Category 5 cabling installed by the volunteers.