Mary Blair Elementary School

Category 5 Handbook

You are visitor number .

Related Links

In early March, 1996, inspired by California's well-organized NetDay, the idea of a Mary Blair NetDay was hatched. Originally, we planned to wire five classrooms with two Category 5 lines each, plus the Media Center with two lines.

With generous support from the PTO, the Student Council, and the Principal, we eventually received enough funding to cable every one of the 23 (twenty-three) full-sized classrooms, except Art and Music. Each classroom was to receive two Category 5 lines and the Media Center was to receive four Category 5 lines.

[Click here to view the floor plan of Mary Blair Elementary School.]

On Saturday, March 30, 1996, about a dozen volunteers worked at the school for three to six hours each. We pulled our first nine cables.

Work continued throughout April, with a small group of volunteers working after school or nights once or twice a week plus Saturday, and with one or two volunteers working many additional afternoons, nights, and Sundays.

On Sunday, April 28, 1996, the volunteers completed termination of the patch panel and the last of the 50 (fifty) Category 5 cables.

At 3:30 PM on Wednesday, May 1, two professional cablers from Collins Control in Fort Collins brought their best test-equipment to test and certify our installation. By 5:15 PM, our new infrastructure was certified as 100% Category 5 compliant!

[Click here to view the floor plan with Category 5 information.]

Since the lead volunteer will not always be available at Mary Blair, the purpose of this handbook is to document the installation guidelines that allowed us to achieve 100% Category 5 compliance.

Obviously, this handbook should be consulted whenever any Category 5 cabling modification is planned or performed.

Less obviously, this handbook should also be consulted whenever any lighting or AC wiring changes are planned or performed.

INDUSTRY STANDARDS

All cables were UL-listed type CMP or MPP (plenum-rated communications cable).

All cables were UTP (unshielded twisted pair), 4 pair, 24 AWG, EIA/TIA 568, verified Category 5.

All terminations at the jacks and at the patch panel were T568B. (AKA AT&T 258A). The jacks and the patch panel were rated as Category 5.

All terminations at the jacks and at the patch panel used 110-style punch-downs.

In most classrooms, the existing IBM Baseband LAN jacks were replaced. The replacement jacks were 6-conductor USOC with 110-style punch-downs. No other modifications of any kind were made to the existing IBM Baseband LAN.

In one or two cases, a modem or voice jack was replaced. The replacement jacks were USOC jacks with 110-style punch-downs.

MBE STANDARDS

Cable designations:

Each cable was uniquely identified and labeled on both ends as it was pulled. Typical designations for the two cables to a classroom were 201/A and 201/B. These labels were removed from the cables as they were punched down on the patch panel. But the labels were generally left on the cables inside the box in the classrooms.

Jack color codes:

The first cable to a classroom (cable A) is always connected to a blue jack.

The second cable (cable B) is always connected to a red jack.

The third cable (Cable C) is connected to a purple jack. (Only the media center has more than two cables at this time.)

The fourth cable (Cable D) is connected to a yellow jack.

Blue, red, purple, and yellow jacks are always rated as Category 5.

The rewired IBM Baseband LAN jacks are white.

The rewired voice-grade (voice, modem, or AT&T Spirit) jacks are ivory.

Patch-panel color codes and positions:

The patch panel is marked with a room number. The color of the markings or the color of the background corresponds to the color of the jack in the classroom.

Patch panel ports for a given room are always adjacent to each other. The ports are always in order from left to right (blue, red, purple, yellow).

Note: This standard ordering is important for those who are colorblind.

Coverplate and jack positions:

Coverplates were always 4- or 6-position ivory.

Unused positions were always filled with ivory blanks.

The Blue jack, if present, is always in the upper left position.

The Red jack, if present, is always in the upper right position.

The White jack, if present, is always in the lower right position.

The Ivory jack, if present, is always in the lower left position.

In several cases, an existing box was mounted horizontally. In this case, the above position scheme was used when installing the jacks in the cover plate. Then the cover plate was rotated 90 degrees and installed over the box.

Note: This standard positioning is important for those who are colorblind.

Parts list:

The patch panels and all jacks and coverplates are manufactured by Leviton Telcom. Leviton part numbers are listed here for reference:

CATEGORY 5 CABLE LENGTH GUIDELINES

EIA/TIA 568 specifies a maximum length of 100 meters (approximately 328 feet) from the hub to the computer. 90 meters (approximately 300 feet) is allowed from the patch panel to the jack in the classroom. 6 meters (approximately 20 feet) is allowed from the hub to the patch panel. 3 meters (approximately 10 feet) is allowed from the jack to the computer.

In an office environment, the 90/6/3 allocation is reasonable. In a 30' x 30' classroom, a 3 meter cable is often unreasonable.

An alternative is to tally the distance of each of the three components of the cabling system. The patch cable connected to the hub and the patch cable connected to the computer must be measured at 120% of their actual length. [Patch cables are more flexible than building wiring, but have poorer electrical characteristics.]

The longest cable run in MBE is currently about 255 feet. In practice, a 30 foot patch cable in the classroom should not strain the Category 5 distance limitations.

CATEGORY 5 CABLE ROUTING GUIDELINES

CATEGORY 5 JACK TERMINATION GUIDELINES

USOC JACK TERMINATION GUIDELINES

CATEGORY 5 PATCH PANEL TERMINATION GUIDELINES

HOW IMPORTANT ARE THE GUIDELINES?

The experts told us that a single major transgression of these guidelines can cause a cable to fail to perform in a Category 5 environment.

A cable might pass, even with a few minor transgressions of these guidelines.

Our policy was to follow the guidelines, except in those few instances where it was extremely difficult to follow them. There are several instances, especially where only one or two cables are involved, where the cable routing guidelines were followed less rigorously.

FUTURE PLANS

Rooms 206 and 208 can be divided into two half-size classrooms or combined to make one full-size classroom. These two rooms are now combined to make one full-size classroom. Room 206 was cabled. Room 208 remains to be cabled.

The volunteers kept some cable on reserve in case of trouble with the testing. After the network was tested, but before the Fire Stop was installed, cables were run to room 207. Room 207 remains to be terminated and tested.

Room 210 is behind its own 1-hour firewall. This room remains to be cabled.

The multipurpose section of the building is behind its own 2-hour firewall. This includes the Music and Art rooms, which remain to be cabled.

The media center needs more ports. It may make sense to install a small hub in lieu of running a number of additional cables.

The only areas cabled were classrooms and the Media Center. Other areas may need to be cabled, but were not considered high priority.

COMPARISON WITH DISTRICT PLANS

General plans for the cabling infrastructure (as well as many other technological topics) are specified in the Thompson School District's "Strategic Plan for Technology -- A Work in Progress".

More details regarding the cabling infrastructure of the schools are contained in the above report's Appendix B "Cyberlink Final Report -- March 1995".

We believe the category 5 cabling the volunteers installed is in perfect harmony with the goals of the Strategic Plan.

We also believe that aside from having a portion of the work done sooner at a fraction of the cost, the category 5 cabling is in close harmony with Appendix B and with Appendix H, the Tactical Implementation Analysis.

The District recognizes that the IBM Baseband LAN is hopelessly obsolete. For Mary Blair Elementary, the strategic plan recommends installation of two Category 5 cables plus one telephone cable into each classroom.

The strategic plan also recommends installation of Category 5 cables in virtually every area of the building, including the custodial office, the kitchen, and the boiler room.

Mary Blair Elementary is listed in Appendix B as being a "Phase 3" school. If ample funding had been available, MBE would have been cabled by June 1998. However, at the time of MBE's NetDay, funding was not available, and the cabling was already a year behind Appendix B's schedule.

The Board of Education is now (circa July 1996) considering a bond issue that would raise money for this and other purposes.

The total cost of cabling MBE is shown in the plan at $51K. Of this, approximately $33.5K is for cabling the 28 classrooms, and the balance is for cabling the Media Center and other areas of the building.

Of the $33.5K designated for cabling the 28 classrooms, $18.6K is for two Category 5 cables per classroom, and $14.9K is for a telephone line to each classroom.

At the time the Cyberlink report was prepared, there was a critical shortage of plenum-rated cable. Therefore, the Cyberlink estimates were for installing non-plenum cable in conduit. Since this shortage has abated, the volunteers chose to install plenum-rated cable without conduit.

The Cyberlink estimates did not include hubs.

Comparison of Costs at Other School Districts

As a point of reference, the California NetDay '96 experts estimated the cost to wire a classroom with two Category 5 ports to be $2,800 per classroom, going through the traditional engineering, bid, and contract process.

The North Carolina NetDay '96 experts estimate their equivalent cost to be $2,250 per classroom.

The Category 5 portion of the MBE portion of the Thompson R2-J Plan works out to about $660 per classroom ($18.6K divided by 28 classrooms).

The MBE volunteers spent less than $125 per classroom, of which the majority of the funds came from the PTO and Student Council.

Telephone Lines to Each Classroom

Telephone lines were not treated as a high priority by the volunteers.

Despite this, the volunteers did bring limited telephone service from the telephone room to the Category 5 patch panel. If a class needs telephone service for a particular lesson (for example for a distance-learning application or a modem connection), telephone service can be brought to that classroom via the patch panel for the duration of the lesson.

The Plan specifies that existing wiring should be reused wherever possible. Long term, the lead volunteer questions whether new telephone cables to each classroom are required.

Every classroom has an IBM Baseband LAN connection, which will be phased out eventually. Therefore, every classroom is already wired with two pairs of better-than-telephone grade cable.

Each classroom's Baseband cable connects to one of four IBM Baseband Hubs at one of three locations throughout the school. Each Baseband Hub can serve up to ten classrooms.

Why not run a 25-pair telephone cable (or five to ten 4-pair Category 3 cables) from the telephone room to the current location of each Baseband Hub. When the old baseband LAN is phased out, splice the old classroom baseband cables onto the new telephone cables.

Even if it is decided to run a separate telephone (or Category 3) cable from the telephone room to each individual classroom, the materials costs should be significantly less than the costs involved for the Category 5 cabling installed by the volunteers.