Gus & Mary's new home at 1915 William Drive Penngrove California

Page 1         Return to index         

Click on the picture to see a full sized image. Use your back button to return here.

Picture2_001.jpg (502485 bytes)

This is the first view of our new lot in Penngrove.

The for sale sign in at the front of the lot

 

Picture2 004.jpg (505596 bytes) This picture is from the back of the lot looking out towards William Drive.
DSCF0999.JPG (493024 bytes)

While the road was under construction we put in a chase for the gas line.

The green stake is the new sewer stub. The white box on the left is the water meter.

DSCF1032.JPG (492589 bytes) Our neighbor Bill, from up the block, used his backhoe to dig trenches for the soils report.
DSCF1075.JPG (490761 bytes) The first mowing of the spring of 2007. The grass is so high I needed a special mower from the rental company. My tool box and tent are at the back of the lot.
DSCF1225w.jpg (46653 bytes) My "new" trailer. It was from Craig's List. FREE and worth every cent.
DSCF1305w.jpg (136436 bytes) The lot is ready for the action to begin. 

Monday September 10, 2007

DSCF1307.JPG (485974 bytes) First equipment arrives at the site. Western Construction is doing the site work.
DSCF1309w.jpg (40915 bytes) The only plant on the site is uprooted. It was in the kitchen and had to go.
DSCF1314w.jpg (50037 bytes) The road grader takes up the grass on the building site.
DSCF1319w.jpg (49634 bytes) Leveling the building pad. One worker uses a rod with a beeper activated by a laser level (out of sight), and another wets down the site to minimize the dust and help compact the soil.
DSCF1329w.jpg (54736 bytes) Starting the sewer trench.
DSCF1331w.jpg (55284 bytes) The sewer trench from another angle.
DSCF1336w.jpg (56602 bytes) Almost to the street. Laser level is on the left.
DSCF1339w.jpg (58859 bytes) Adding a 6 inch layer of sand to the trench. 
DSCF1346w.jpg (55531 bytes) The sewer pipe lays the sand and will be covered after inspection with 10 more inches of sand.
DSCF1351w.jpg (60460 bytes) Starting to dig the trench for the water line.
DSCF1355w.jpg (14202 bytes) End of the day. Small red/orange flags are pier locations.
DSCF1360w.jpg (65001 bytes) Filling the water line trench with base rock under the future driveway.
DSCF1361w.jpg (69015 bytes) My first plumbing pipe. This goes under the deck and foundation wall. Vertical pipe is the cleanout. It will be shortened to deck level later on.
DSCF1375w.jpg (109752 bytes) Sept. 18th

The first few holes are drilled for the foundation grade beam and porch posts.

DSCF1379w.jpg (89354 bytes) Starting on the middle row, supporting the girder under the floor joists.
DSCF1386w.jpg (108360 bytes) This is a very dusty, dirty job. Maybe I should have called Mike Rowe.
DSCF1402w.jpg (119653 bytes) OK, the piers are drilled and I've cleaned off one outside porch pier and installed the rebar cage.
DSCF1409w.jpg (102963 bytes) Mile of Western Construction is starting the driveway. Sonoma County Fire Safe Standards require 12" of base rock.
DSCF1412.JPG (502572 bytes) All of the rebar cages are installed waiting for the building inspector.

Sept. 19th

DSCF1415w.jpg (94322 bytes) PG&E requires a special type of sand around their pipes. Three loads are delivered Thursday morning Sept. 20th.
DSCF1416w.jpg (107769 bytes) Hand digging reveals telephone cables and under them a 12KV conduit.
DSCF1419w.jpg (86977 bytes) The trench has to be dug 3 feet from the water main at the edge of the pavement. The ditch is just above the flow line of the culvert. Notice how clean they keep the street.
DSCF1421w.jpg (104726 bytes) Late in the day shot so lighting is not good. Notice the new conduit and the black phone cables and yellow gas line. All hand digging around these parts.
DSCF1425w.jpg (79467 bytes) Here the crew is compacting the base rock in my neighbor's driveway.
DSCF1426w.jpg (116072 bytes) The trench takes a jog here to get out of the culvert. The angle part is all hand dug. Phone, gas and high voltage lines run thru this part of the trench. The Phone box is the gray thing to the left.
DSCF1427w.jpg (102864 bytes) This picture shows the trench from start to finish today. Before the crew was done for the day they had put barricades up along the street and washed the street with the water truck spray.
DSCF1428w.jpg (115070 bytes) September 21st, PG&E sand covers the pipes in the trench. Mike is compacting the dirt cover. The green pipe is Lance's sewer cleanout, the gray pipes are my electrical, cable and phone conduits.
DSCF1430w.jpg (124095 bytes) Close-up of the transition ditch from street edge, to the other side of the drainage ditch. Sheep's foot compactor on the excavator. Lots of hand work involved here.
DSCF1431w.jpg (92755 bytes) Base rock is tamped over the PG&E sand here since the location is in the drainage ditch.
DSCF1434w.jpg (76655 bytes) I'm ready for concrete, it is getting close to the 2:00 time, but no truck is in site. It won't be this still in 30 minutes.
DSCF1435w.jpg (91593 bytes) The first 9 yards are poured. It came so fast that I did not get pictures of the pouring or of the first truck. There is always too much work during a pour.
DSCF1439w.jpg (68205 bytes) The crew has almost finished the street-side ditch backfill. It looks like new, but actually better than it was before the dig.
DSCF1440w.jpg (58201 bytes) The second truck has arrived, Jorg is walking it in, Jim Pedone is leaving . He was a surprise helper during the first pour.
DSCF1444w.jpg (75691 bytes) The second Shamrock truck is backing up to the edge of the foundation piers. I was very tired after this second pour, with Mike's laborer's help we were done by 4:30.
DSCF1446w.jpg (97843 bytes) I finished up on Saturday around 1:00 PM with a half a yard is a small mixer. Two holes needed to be filled in and re-drilled.
DSCF1448w.jpg (96992 bytes) I set string lines over the holes to determine the location of the foundation walls and deck piers. At this point on Saturday I had cleared the dirt from the hole drilling off of one side only.
DSCF1452w.jpg (102293 bytes) Sunday I finished clearing the dirt from under the floor and actually set the first foundation stakes. Mary came to the lot and helped me check square.
DSCF1455w.jpg (129195 bytes) Monday September 24th I put up the first foundation wall.
DSCF1456w.jpg (220196 bytes) Mike's skid steer tractor saved me three days work by moving two piles of lumber inside the foundation area. He is digging out the driveway in the background.
DSCF1459w.jpg (94423 bytes) Mike's crew is laying out the filter cloth. A 3 inch layer of rock will be spread over this and then watered and rolled. The process will repeat until there is 12 inches of rock in the driveway.
DSCF1461w.jpg (85938 bytes) Base rock is stockpiled along side of the driveway. A dump truck cannot yet drive over the cloth. After this is rolled out and another layer applied then base rock can be dumped directly on the driveway.
DSCF1462w.jpg (88293 bytes) Starting to build the second foundation wall. This goes fast as I am using both 12 and 24 foot long boards.
DSCF1464w.jpg (79405 bytes) End of the driveway and beginning of the garage pad. The garage will be built later, much later.
DSCF1466w.jpg (91343 bytes) End of today's work. Second wall is finished and the third wall started. The drill rig returned this afternoon and three new holes were dug. I cleaned up most of the dirt, but there is still lots of shoveling left to do.
DSCF1468w.jpg (91937 bytes) On September 25th I finished the outside of the forms. Lupe is on the vibrating roller compacting the driveway gravel.
DSCF1469w.jpg (76084 bytes) I bent the steel that came out of the piers so that it will be at the top of the grade beam. Thanks to Jeff Millerick for the tip on bending.
DSCF1475w.jpg (95623 bytes) September 26th. I've started to double the forms making up the grade beams.
DSCF1478w.jpg (69986 bytes) Late in the day shot, long shadows. Two walls are doubled. The heat today was almost unbearable.
DSCF1479w.jpg (94436 bytes) Lots of gravel was dumped in the driveway today.
DSCF1481w.jpg (85214 bytes) September 28th, all the forms are doubled, bolts are installed and I am waiting for the Inspectors. Both the soils engineer and county building inspector have to sign off the work before I can pour concrete.
DSCF1482w.jpg (87372 bytes) Both inspectors passed the work. Jorg will be here later today, to pick up the rebar bender sitting on the wall. I've installed the bracing and am now ready to go. I will have help next Tuesday to pour.
DSCF1494w.jpg (98290 bytes) On October 1st I poured some of the piers. I got 3/4 of a yard on mix in a trailer.
DSCF1497w.jpg (98221 bytes) This picture shows the piers with the concrete and anchors done.
DSCF1499w.jpg (69744 bytes) October 2nd; the day started with the driveway being smoothed out.
DSCF1501w.jpg (89760 bytes) Here the concrete pour is complete. We vibrated the walls with the tool shown on the ground in this picture.
DSCF1503w.jpg (96479 bytes) Close-up of the grade beams full of concrete.
DSCF1504w.jpg (88173 bytes) Almost the end of the day. I still have to break up the concrete that is against the form boards. I worked till the sun set tonight.
DSCF1505w.jpg (84619 bytes) October 4th. The walls are stripped and the ties bent down (saves the skin on my legs). I still have to clean the concrete from the form boards and stack them up for later use.
DSCF1507w.jpg (73660 bytes) October 5th. The mudsills (brown/red boards) are in place, I've cleaned up the concrete from the inside of the foundation. This will make crawling under the floor so much easier.
DSCF1508w.jpg (78004 bytes) I am ready for Mary to show up and we can check the elevation of the top of the forms. It threatened rain late this afternoon, but only a few drops fell.
DSCF1509w.jpg (57363 bytes) Looking down the driveway from the street. Ominous clouds fill the sky.
DSCF1523w.jpg (90882 bytes) The center piers and girder have been installed, the last of the deck piers are poured and the roof drainage pipe is installed. 10-9-07
DSCF1525w.jpg (99054 bytes) The first two floor joists are installed. After I set the girder I decided to grout the mudsills to within a 3/16" tolerance. October 11th I finally got to the floor joists.
DSCF1527w.jpg (79642 bytes) End of the first day of floor joists. This is the master bathroom; the next joist will be 3 1/2" away for the wall and plumbing will be in between the joists.
DSCF1538w.jpg (68840 bytes) It rained all day Friday. Saturday was a Caboose Work day so I only installed a few joists, but on Sunday the weather cooperated and I got past the half way mark. End of the day 10-14-07, first joists of the entry and kitchen are installed.
DSCF1539w.jpg (79007 bytes) Picture taken on 10-18-07. All but the last two floor joists are installed. They arrived while I was working at the NWPRRHS Library.
DSCF1541w.jpg (60005 bytes) Later that day I installed the last two I Joists and the rim joist.
DSCF1542w.jpg (79309 bytes) This is the first of two under-floor access points. It is in the master bedroom closet.
DSCF1548w.jpg (75673 bytes) This is the first of the siding; it will be under the ledger joist of the deck. I installed galvanized screen mesh over the rim to make the vents.
DSCF1553w.jpg (84311 bytes) I installed 1x4 boards to keep the I joists straight and to stiffen them up. The black vertical poles are the frame for the electrical meter.
DSCF1554w.jpg (90275 bytes) 10-23-07 started the plumbing in earnest today. This is the work area for the main bathroom. I finished the laundry and kitchen and started on the bath today.
DSCF1555w.jpg (85582 bytes) Under-floor shot of the plumbing. I have to re-do the pipes on the far left. My neighbor (a retired plumber) spotted a rookie mistake. The pipe coming towards you is the line for the kitchen sink
DSCF1558w.jpg (92684 bytes) The front or South wall of the house. The deck ledger is bolted to the rim, and the drainage pipe is installed, all I need now is backfill.