Home | First Views of Property | Starting Work | Building the Foundation | Finishing the Foundation | Log Arrival | Making Progress | Subfloor and first logs | Logs Going UP | First Floor Walls UP | Starting the Second Floor | Roof Progress | Narrative | Providers of Material and Labor | Questions or Comments?
Building a Log Home--Storm Castle Ridge
Making Progress

September 2005 is moving along quickly.  We have had a long dry summer--beautiful weather for building--but minor delays have slowed us down.  Finally, we are starting to make some progress again.

The third load of logs arrived from Montana.  Logs were heavier than expected so not all the building materials could be shipped on this load.  The final shipment of materials is scheduled for early October.

morelogs.jpg

morelogs2.jpg

buildingmaterials.jpg

Kurt Haglund taking inventory of the materials from Rocky Mountain Log Homes.  Every log, each piece of wood, each box of material had to be inventoried as it arrived.

kurttakinginventory.jpg

The plumber, Dennis, of D&D Plumbing (304.822.3299) of Romney, WV installed the below grade plumbing.  Here is a picture of the septic pipe before connected under the foundation followed by a view from outside the foundation.

insidefoundation--septicline.jpg

ditchforsepticline.jpg

The outside connection was completed by Hart Excavating, the company that installed the septic field.

waterline.jpg

This picture shows the water line coming in through the foundation.  The well was drilled in early spring by Miller Bros Well Drilling.  Kurt Haglund suggested that we have the well drilled before laying out the house to make sure water was available at our proposed house site.  A simple and commonsense suggestion but one that many people do not follow--we did.  After drilling the well, Miller Bros told us we had 40 gal a min flow, enough water for a small community.  When the company came back to bring the water line through the foundation, someone made a small error in drilling through the foundation.  If you look closely you can see three holes instead of the one needed for the waterline.  Miller Bros repaired this when they installed the water tank later.

thebasementfloor.jpg

After some delays, the basement floor was poured by Hurt Construction (403.268.2909).

basementfloor.jpg

When Dennis was installing the below grade plumbing, he also roughed in a full bath for the basement (just in case we ever wanted it).

roughinplumbing.jpg

At first, we planned on setting up temporary electric to the house site, but after discussing the work with Jerry Sanders (Sanders Electric, 304.788.2493, Keyser, WV), we decided to have the permanent panel boxes installed.  Jerry said it would be no problem to do it that way and it would save both money and time.  He installed 2 panel boxes in anticipation of the 400 amp service Alleghany Power would be installing.

panelboxes.jpg

Just as we start getting close to subfloor construction, storms begin to move into the area.

stormsapproaching.jpg

The crew from Alleghany Power working on the power linesElectric to the site was connected on 14 October 2005.

electricwork.jpg