More of the same. This is a better view showing the footer pads that will support the steel columns and beams. The concrete footer stops at the rear because this is where the stud framing will begin for the walk-out wall. The grade at the walk-out is not yet complete - it will be dropped nearly two feet. The silver items in the upper left are thermal blankets that will be used to cover the footing sites to prevent frost from forming so that concrete can be poured.