Gas Turbine NOx Reduction Retrofit
James Seebold
Chevron Research & Technology Company
James Bloomquist
Chevron North America Exploration & Production Company
Tim Shippy
Peerless Mfg. Co.
Abstract
Chevron’s Eastridge Cogeneration Plant, located in
the San Joaquin Valley in the Kern River
Field near Bakersfield, California, produces steam for thermally enhanced oil recovery
and electricity to the utility grid. To meet San Joaquin Valley Air Pollution
Control District NOx emissions rules, two General Electric LM2500 combustion gas turbines needed the addition of selective
catalytic reduction (SCR) flue gas treatment systems. This “major surgery” retrofit project sets a benchmark for
effective decision analysis, front-end-engineering and safe, smooth field execution.
Looking to the future beyond the
current rules, the equipment is sized and ready to go to comply
easily with future reductions.
This paper briefly describes the process from beginning
to end. Those who may face such retrofits in the future but lack experience or who would like to improve their previous performance
may benefit from Chevron Eastridge’s learnings. With good planning, gas
turbine SCR retrofits can be accomplished at reasonable cost and with minimal disruption to energy operations. The project’s
identification and qualification of a full-service domestic SCR catalyst supplier,
fully capable of supplying all catalyst services importantly including catalyst activity testing (anybody’s catalyst), benefits all Chevron operations both upstream and downstream with existing or future
SCRs; no longer must service be provided from Japan. Thus, the project is pleased
not only to have met and exceeded its own goals but also to have been of service to the entire corporation. Shutdowns limited to a stunning 5 days for major field modifications
minimized the disruption to electricity and steam supply and kept both external and internal customers happy. Completed ahead of schedule and under budget, the 11-month project and 63-day construction spans were remarkable
by any standard!
Introduction
At the Eastridge Cogeneration Plant, two General Electric
LM2500 combustion gas turbines needed selective catalytic reduction (SCR) flue gas treatment systems to meet San Joaquin Valley
Air Pollution Control District NOx Emissions Rule 4703 requiring reduction of the current <42 ppm NOx emissions to <12
ppm (71% reduction). By looking to the future, the equipment was sized to readily
meet foreseeable emissions limits. Only the installation of additional catalyst material and increased ammonia flow (extra space in the reactor
module and extra pump capacity provided) will be needed in order to achieve emissions as low as <3 ppm or 90% reduction. Peerless Mfg. Co., America's leading SCR system supplier, was awarded
the turnkey contract to design and supply the SCR equipment; ARB Inc. was selected by Peerless to carry out the construction. The team’s project management, design, field service and design support were
outstanding. Completed ahead of schedule and under budget, the 11-month project and 63-day construction spans were remarkable
by any standard. Shutdowns were limited to a stunning 5 days for major field modifications that minimized the disruption to electricity
and steam supply and kept both external and internal customers happy. Here’s
a thumbnail sketch of the major field modifications:
· Prior to shutdown dug and poured new foundations, some under existing ducts
· Shut down the unit and moved the boiler feedwater metering skids
· Decommissioned and abandoned in place tube rows at the end of Economizer II to get the right SCR reaction
temperature
· Cut the duct between economizers
· Moved and set the stack, duct and Economizer I (the latter requiring a 90 ton jack and roll) on new foundations
to make room for the SCR reactor module and new downstream economizer (to the regain steam generating capacity lost in Economizer
II tube abandonment)
· Installed empty SCR reactor module and new economizer (60 ton lift)
· Buttoned the whole thing back up and started generating electricity and steam again at the old permit
condition, while system checks were performed
· Loaded catalyst and started the ammonia upon completion of the ammonia flow control skids and all monitoring
and control instrumentation upgrades
The project’s identification and qualification
of a full-service domestic SCR catalyst supplier will benefit all Chevron operations
both upstream and downstream with existing or future SCRs. Fully capable of supplying all catalyst services importantly including catalyst activity testing (anybody’s catalyst), Cormetech Inc., Durham, NC aspired to become the world’s leading SCR catalyst
supplier and, with the acquisition of a huge Tennessee Valley Authority contract has pretty much achieved that world class
status. No longer must service be provided from Japan. Thus, the project is pleased not only to have met
and exceeded its own goals but also to have been of service to the entire corporation.
Thermal Modeling
Accessing the optimum catalyst reaction temperature
is the key to NOx reduction performance for any SCR retrofit. Accordingly, during
the front end engineering phase, the project contracted with TechnipUSA to do various conceptual studies including a flue
gas thermal model. Shown schematically in Figure 2 are the thermal modeling predictions
together with the actual field measurements and physical locations along the length of the flue gas path. For reference, a photograph of Unit B as shown in Figure 1, is in the same orientation
as the schematic in Figure 2.
As shown, predictions were made for both no
duct burner firing and full duct burner firing and, for both, under clean and two fouled heat transfer surface conditions.
There was good agreement with actually measured temperatures. Not surprisingly, the units were found to be operating somewhere between “clean” and “uniform
fouling” and closer to the latter.
Inevitably, it seems, the optimum catalyst
temperature range for so-called “standard” SCRs (ca.500°F-750°F) is found somewhere in the middle of one of the heat recovery sections and so it was in this case. This implies major surgery and heavy-duty component rearrangement.
So, being well-experienced with the use of “Low
Temperature” SCR (ca.350°F-500°F) designs, we looked carefully at the much physically cleaner LTSCR option during the front
end engineering phase of the project. Regretfully, the flue gas temperature was
simply too low (i.e., the cogeneration plant is simply “too”
efficient) for a simple end-of-pipe design to work effectively; and, the reheat, re-recovery
option with which we are, regretfully, also well-experienced made neither economic nor constructability
sense.
Similarly, the easily-accessible upstream temperatures
were simply too high for application of “high temperature” SCR technology.
Accordingly, the project proponents buckled down to a major surgery, hammer and tongs, brute strength and awkwardness
twin field retrofit and got after it.
Safety, Total Cost and Environmental
Cost-Effectiveness
Despite the
fact that the Eastridge retrofit demanded complex heavy-lift cramped-quarters field construction, the entire project was carried
out with zero incidents or accidents. This is attributable to an excellent Safety Plan developed
at the outset that was consistently reinforced by management and enthusiastically supported by all hands.
The total “all-in” cost of the
project to the stockholders (including all company costs) was $3.25-million. But in computing the environmental cost-effectiveness,
it is important to recognize that advantage was taken of the opportunity to completely modernize the facility by upgrading
the turbine controls, control room displays and other infrastructure. Those improvements
are unrelated to NOx emission reduction and their cost is appropriately excluded
to get a fair assessment of NOx reduction cost-effectiveness. Restricting attention
to the environmental portion of the project, the total installed cost of the SCR retrofit including all company costs was
$2.3-million.
The annualized total installed cost ($/yr), which in the San Joaquin Valley is taken to be amortized at 10 years and
10% rate of return, is 16.3% of the total installed cost ($). For SCR, annual
operating costs and annual maintenance costs are nearly negligible (by comparison) and are commonly taken to be 10-20% and
~5%, respectively, of the total installed cost. Thus, annual operating and maintenance
costs typically increase the annualized total installed cost ($/yr) by
15-25% or to 0.19-0.20($) so we shall take 0.195($) to estimate the annualized total cost of ownership ($/yr) = 0.195x$2.3-million
= $448,500/yr.
The annual NOx reduction (tons/yr) being achieved by the Eastridge units is 350 tons/yr. The cost effectiveness ($/ton) then becomes the annualized total cost of ownership ($/yr)
divided by the annual NOx reduction (tons/yr) = $1,281/ton.
Many NOx
reduction regulatory mandates have been carried out at much higher (i.e., less favorable) cost-effectiveness. While the project’s
environmental cost-effectiveness is exemplary, regulators and others will do well to remember that cost-effectiveness is merely
a figure of merit that may be used to facilitate comparison with other means of
achieving the same NOx reduction mandate or with the environmental effectiveness
of other projects.
“Cost-effectiveness”
per se hardly drives the business decision and never
provides, in and of itself, financial justification for project execution. It
is true, however, that for a given regulatory mandate, the project planning process that produces the lowest total cost of
ownership (annualized capital cost plus annual operating and maintenance costs) will also produce the lowest environmental
cost-effectiveness.
In any
event, considering that individual environmental projects
ideally contribute some measure of health or wellbeing improvements, they do not directly affect
the corporate bottom line. Thus, public stockholders and corporate directors alike favor
NOx reduction projects that are carried out at the lowest possible cost-effectiveness!
Project Development and Execution Tools
At this point it seems useful to step back
to the early conceptual days of the Eastridge project to mention briefly the various project management and development tools
that were used to good advantage in producing a winner for stockholders and the consuming public alike. Not least among these was “DA” (Decision Analysis) which answered the question, for example, “Given the variety of NOx reduction technologies that are available, which ones are technically and
economically viable candidates and, of those, which NOx reduction technology should be installed?”
Without belaboring
the discussion, among the candidate technologies were dry low NOx (DLN), selective non-catalytic reduction (SNCR), and three
flavors of selective catalytic reduction flue gas treatment systems; viz., high-temperature
(HTSCR), low-temperature (LTSCR) and standard temperature (SCR).
Throughout the project from beginning to end, “CPDEP” principles
and practice greatly contributed to the project’s stunning success. The Chevron Project Development and Execution Process is Chevron's common framework for asset or project development and execution. This five-phase model
helps us to make more effective use of our resources; viz., people, capital, and
technology. CPDEP is a generic corporate project management and development process
that can be adapted to meet the needs of specific operating company (“opco”) lines of business.
A project that goes through a full life cycle
results in the development and delivery of a product. The product that is delivered could be something like a modernized refinery,
a dismantled facility, a network, or an application, depending on an opco's line of business.
At Chevron Eastridge, the “SCR retrofit” was hardly limited to that most visible element of the work. It included a complete modernization of the cogeneration facility including turbine
controls, displays and integration. In addition to DA and CPDEP, among the other
corporate development and execution tools that directly contributed not only to project clarity but also to substantial cost
reductions were “PEP” (Project Execution Plan), “FEL” (Front End Loading) and “IPA” (Independent
Project Analysis).
The journey from dreams to reality is reflected in the perception of cost to
achieve the desired result. The “reduction” of the perceived cost,
largely owing to the application of management tools at each stage of development of the project, is striking:
·
$14-million Original Estimate – Initial DA
·
$26-million
- 3rd Party Engineering Estimate (Oops!)
·
$14-million – In-house Project Resources Check
Estimate
·
$8-million DA / CPDEP / PEP
·
$6-million CPDEP / PEP / FEL / IPA
·
$4-million CPDEP / PEP / FEL
· $3.25-million AFE (“Authorization
For Expenditure,”
the Corporate-management blessed “Thou Shalt Not Exceed” number!)
Facility Modernization
During the SCR retrofit, plant management took advantage
of the opportunity to modernize the Eastridge Cogeneration Plant control system into a very powerful SCADA (“Supervisor Control Automated
Data Acquisition”)
system. Turbine controls, distributive control system (DCS) and continuous emissions
monitoring systems (CEMS) alike were upgraded with the latest technology. Moreover,
these individual systems were linked to a common network to facilitate gathering, exchanging and storing data. This allows
operators and engineers to utilize not only current data but also historical data in event identification, performance and
efficiency evaluations.
Lastly, an unexpected but welcome benefit emerged
from this retrofit project. Maintenance for this facility had been developed around the timeframe to perform both mechanical
and instrumentation work. By replacing the former analog systems in the turbine governor control and DCS system with digital
equipment, the same people working together have reduced the overall maintenance downtime by a remarkable 50%. This includes
the additional maintenance burden associated with the new SCR systems which operators, mechanics and managers alike are pleased to report is minimal!
Now that the project is behind us, the visiting
executives who are unfamiliar with the project ask, “What did you do?” and the plant operators notice no change
except perhaps that operation has gotten a little easier.
In short, that’s the Chevron definition of
a “good retrofit;” viz., one that just rocks along doing its job and
nobody really notices. That’s just fine by us!
For
a .pdf of the complete paper email
and include the paper title so I know
what to send!