7/6/04
Pella windows are delivered
|
7/27/04
Upstairs masonry chimney roughed in
|
8/2/04
Radiant heat maniford and tubing for the basement
|
8/3/04
Plumbing drains roughed in
|
8/20/04
Much of the electrical is now installed
|
9/2/04
The well is started
|
9/3/04
Zak & Trevor installed lots of orange conduit
|
9/15/04
The well is dug and the pump is in, we have water now
|
11/4/04
Spa tub installed in the Master Bath
|
11/26/04
Video, Network, Telephone board in mechanical room
|
12/14/04
Ductwork going into the loft kneewall
|
12/14/04
Radiant heat tubing in the master bath shower wall
|
12/22/04
Radiant tubes and transfer plates going into the bottom of the first floor
|
12/30/04
1,000 gallon LP gas tank installed
|
1/19/05
Boiler and radiant heat piping installation started
|
4/27/05
Final Video, Network, Telephone configuration
|
4/27/05
Boiler and radiant heat
|
4/27/05
Final water treatment configuration
|
4/27/05
Final electrical configuration
|
|