Interior: Jun 2004 - Apr 2005

7/6/04
Basement floor insulation in preparation for radiant floor heat and concrete slab

7/8/04
Lots of interior framing is done

7/27/04
Most of the interior framing is completed

8/10/04
Basement floor was poured on Monday

8/12/04
Nothing like child labor to get the frame oiled

8/20/04
Still working the boys hard, glad they're not afraid of heights

10/12/04
Basement garage floor poured on Tuesday and upper garage floor poured on Wednesday

11/4/04
Timbers masked and taped in prep for drywall and painting

11/12/04
First floor mechanicals are in, pretty much ready for insulation and drywall

12/2/04
Stone going up on the first floor
fireplace

12/10/04
First floor
fireplace completed

12/31/04
Most of the drywall is installed

2/4/05
Finally ready for painting

2/8/05
Primer done and ceiling paint going up

2/11/05
Paining finished

2/11/05
Paining finished

2/17/05
Master bath tile set

2/18/05
Trim well underway

3/4/05
Master bath tile in place

3/4/05
Main stairs installed

3/8/05
Railing added to the main stairs

3/11/05
Stairs and railing complete

3/17/05
Hardwood flooring going down

3/28/05
Some lights installed

3/30/05
Hardwood floors being finished

4/5/05
Carpet is now installed in the loft

4/21/05
Entry medalion is in place

4/22/05
Just about finished

4/22/05
Just about finished, looking towarsd the kitchen