6/15/04
Some of the roofing paper is up
|
7/6/04
Tyvek Stucco Wrap is up
|
7/23/04
Shingles are mostly up and windows are in
|
8/3/04
Shingles are done and upstairs doors are in
|
8/20/04
Front entry bent is spar varnished
|
11/4/04 Foam going up around the outside in preparation for Dryvit and Stone
|
11/26/04
Foam mostly finished and about half the scratch coat
|

12/11/04
Exterior Dryvit is completed
|
|

12/22/04
Getting the driveway prepped
|

3/21/05
Working on the entry
|

4/1/05
Good progress today on the entry stone
|

4/15/05
Lit up and almost ready to move into
|